01/01/2024 - Monday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-Committee Meeting #2 - Production Chemicals IP 2024

-Continue my work regarding Graphic motions and Media management for IP2024.

02/01/2024 - Tuesday 

-IP2024 day 1.

-morning session is SWOT(Strengths, Weakness, Opportunity and Threat) session.

-Evening session is FA(Focus Accountability) session lead by coach Firdaus. 

03/01/2024 - Wednesday

-IP2024 Day 2.

-Morning sessions is IP session.

-Evening session is Farewell Hj. Azam sessions. 

04/01/2024 - Thursday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment. 

-Continue my work regarding Action Item tracker system utilizing powerbi and powerapp.

07/01/2024 - Sunday

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment, An Error Trap Leads to a Catastrophe.

  • If you notice equipment that looks similar but operates differently, tell your supervisor. There may be several ways to remove the error trap:

    • Add pictures to improve operating procedures by showing the correct position or alignment for the valves or other equipment.

    •  Replace some valves so they all operate the same way and make such changes using Management of Change (MOC).

  • Where poor lighting makes operations more difficult, recommend improving the lighting in the area to reduce errors and improve general safety. (Again, follow MOC)

  • Some companies consider error traps near-misses and want them reported using a near-miss or other reporting form.

  • Also see the June 2006 Beacon for another valve error incident.

08/01/2024 - Monday

-MC

09/01/2024 - Tuesday

-Commenced the day by convening in the Control Room for a morning meeting at 8:30 am; however, it was noted with regret that there was no dedicated time allocated for discussions on safety and Health, Safety, and Environment (HSE) matters.

-Subsequently, delved into the intricacies of advancing the Action Item Tracker system, dedicating focused efforts to harness the capabilities of PowerBI and PowerApps. This endeavor involved a meticulous exploration of the functionalities and features within these powerful tools, aiming to enhance the overall efficiency and effectiveness of the tracking system.

10/01/2024 - Wednesday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment. 

-Continue my work regarding Action Item tracker system utilizing powerbi and powerapp.

11/01/2024 - Thursday

-Began the day with a morning meeting in Control Room at 8:30 am, unfortunately, there was no discussion about safety and HSE.

-Continued my efforts by working on the Action Item Tracker system, making use of PowerBI and PowerApps.

14/01/2024 - Sunday

-Began the day with a morning meeting in Control Room at 8:30 am, unfortunately, there was 1 discussion about safety and HSE, related to Fingers injury while preparing for painting job resulted in Loss Time Injury(LTI).

  • have you ensured that all portable tools/equipment have been inspected and safe for use?

  • Are the personnel aware of hazards and precautions when working with rotating equipment. 

  • Have you identified the potentials line of fire before starting any work to ensure body parts are kept away from danger?

  • Have you use correct personnel Protective Equipment(PPE) for the tasks identified in the risk assessment?

-Continued my efforts by working on the Action Item Tracker system, making use of PowerBI and PowerApps.

15/01/2024 - Monday

-Began the day with a morning meeting in Control Room at 8:30 am, unfortunately, there was no discussion about safety and HSE.

-Continued my efforts by working on the Action Item Tracker system, making use of PowerBI and PowerApps.

-Framing my Gantt chart for the Action Item project named MyAction to see the flow and process stage of the project.

16/01/2024 - Tuesday

-Began the day with a morning meeting in Control Room at 8:30 am, unfortunately, there was no discussion about safety and HSE.

-Continued my efforts by working on the Action Item Tracker system, making use of PowerBI and PowerApps.

-PC OGD NMI ATTACHMENT CHECKLIST 7 related to relevant work process reviewed by En.Roslin for the morning session and for the evening session, the fasilitator is En.Zul as the safety warden.

17/01/2024 - Wednesday

-Began the day with a morning meeting in Control Room at 8:30 am, unfortunately, there was no discussion about safety and HSE.

-Continued my efforts by working on the Action Item Tracker system, making use of PowerBI and PowerApps.

-Make a draft about functional requirements and non-functional requirements for MyAction.

18/01/2024 - Thursday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-Drawing the flow chart for all the MyAction requirements.

-Presentation EOA certificate by one of the colleague.

-Starting to sketching low-fidelity prototype.

21/01/2024 - Sunday

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment which is Fatality Incident During Online Leak Sealing Work. Lesson Learnt:

  • Incorporate detailed assurance requirements of QA/QC for online leak sealing work including engineering design, fabrication, material selection and installation in the invitation to Bid(ITB)/contract document.

  • Improve the Online Leak Sealing Procedure by incorporating the specific assurance requirements for the QA/QC in engineering design, fabrication, materials delivery and installation.

  • revise the Emergency Response Procedure (ERP) to manage in the involvement of local authorities during the period of accident i.e. roles of Police Department.

  • Let's strive towards Mission:zero-Possible to prevent future incidents.

-Lead the Coffee Talk #1 Work Quality & Yaseen Recital.

22/01/2024 - Monday

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment which is regarding handling human error, human factor management and failure. 

-Assigned new task to transform the data from excel to readable powerbi dashboard under the project: Chemicals Project and Study Status. 

23/01/2024 - Tuesday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-Monthly eIDEA Review meeting.

-Finalizing the media presentation for the farewell ceremony of the colleagues on 24/01/24.

-Updating powerbi dashboard for chemicals project/study list.

24/01/2024 - Wednesday

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-KTSB DRUMMING FACILITY (LOT N) SITE VISIT. Exploring the storage area of the chemicals product before exporting it to the clients.

-LOT N drumming Familiarization.

-Chemicals Department Monthly Meeting.

-Farewell ceremony for the colleagues. 

25/01/2024 - Thursday 

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment. A helicopter ditching incident occurred at offshore Bintulu in between two platforms which resulted in one fatality involving PETRONAS staff. The incident happened when the helicopter encountered hydraulic system failure which escalated into fire hence resulted in the decision to conduct the controlled ditching into the sea.

-Presentation of contaminant in crude butanol at chemicals library.

-Continue my project using Power App.

28/01/2024 - Sunday 

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment. Striking the right Balance by Mr. Yusri.

-Continue my project using Power App.

-Receiving new powerbi dashboard project which is to visualize isotainer costing data.

29/01/2024 - Monday 

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-Continue my project using Power App.

-Short meeting with PETRONAS OE DIGITAL related to the powerApp data pump issues.

30/01/2024 - Tuesday 

-Started the day with Morning meeting at control room 8:30 am. There no safety and HSE moment.

-Continue my project using Power App and PowerBi.

31/01/2024 - Wednesday 

-Started the day with Morning meeting at control room 8:30 am. There 1 safety and HSE moment. Which is regarding chemical spillage.

-Continue my project using Power App and PowerBi.

-Butanol process and operation overview by En. Hasnul.

@wanafwan